25/09/2018 10:19:00
16/10/2019 09:52:00
10/10/2019 13:45:00
20/08/2019 13:23:00
14/08/2019 13:55:00
29/04/2019 14:15:00
06/04/2019 18:08:00
19/03/2019 15:18:00
25/02/2019 12:19:00
15/02/2019 15:07:00
11/02/2019 13:55:00
21/01/2019 14:06:00
04/01/2019 09:13:00
23/12/2018 18:06:00
20/12/2018 16:58:00
19/12/2018 17:30:00
10/12/2018 14:24:00
19/11/2018 14:12:00
12/11/2018 12:34:00
05/11/2018 07:21:00
26/10/2018 12:53:00
02/10/2018 18:01:00
25/09/2018 10:19:00
21/09/2018 10:48:00
14/09/2018 10:55:00
03/09/2018 11:04:00
26/07/2018 09:05:00
22/06/2018 09:26:00
21/06/2018 09:40:00
04/06/2018 14:56:00
28/05/2018 10:36:00
07/05/2018 14:44:00
24/04/2018 09:13:00
18/04/2018 14:49:00
12/04/2018 08:57:00
21/03/2018 14:59:00
21/03/2018 14:49:00
21/03/2018 14:36:00
21/03/2018 14:22:00
21/03/2018 14:13:00
21/03/2018 14:03:00
21/03/2018 13:06:00
15/01/2018 08:58:00
05/01/2018 12:09:00
25/12/2017 09:49:00
13/12/2017 14:23:00
01/12/2017 11:10:00
30/11/2017 14:48:00
29/11/2017 14:33:00
24/11/2017 14:35:00
24/11/2017 13:35:00
24/11/2017 13:24:00
27/10/2017 16:41:00
28/09/2017 12:25:00
27/07/2017 17:14:00
27/07/2017 15:14:00
27/07/2017 14:43:00
26/07/2017 14:12:00
26/07/2017 12:02:00
25/05/2017 13:24:00
25/05/2017 10:12:00
15/05/2017 12:26:00
04/05/2017 14:19:00
18/04/2017 14:22:00
18/04/2017 10:01:00
11/04/2017 14:48:00
10/04/2017 14:19:00
17/03/2017 13:14:00
14/03/2017 12:28:00
09/03/2017 19:52:00
19/01/2017 13:17:00
28/10/2016 14:21:00
10/10/2016 12:37:00
22/05/2015 15:08:00
12/03/2015 08:43:00
23/02/2015 08:41:00
07/01/2015 15:20:00
13/11/2013 10:50:00
22/10/2013 12:01:00
02/02/2012 20:57:00
04/10/2011 20:58:00
26/09/2011 03:57:00
03/05/2011 18:46:00
11/02/2011 03:39:00
20/12/2010 20:20:00
03/12/2010 10:54:00
30/11/2010 20:55:00
29/11/2010 20:54:00
It is about a project
of the Energy plant worth about 35.000 BAM, based on which the complete
reparation of all defects, reported on the GIKIL’s 35kV long power lines, has
been completed.
"Unfortunately,
we cannot have a lot of influence on the breakdowns caused by the interruption
in the power supply from Puračić substation, because Elektroprivreda BiH is
responsible for maintaining of this distributive network, but we can improve
the condition of it what is in GIKIL. With this aim, the company Umel -
Dalekovodmontaža d.o.o. Tuzla has been engaged, which performed reparation
works for us at the 35kV SS Puračić-SS Azotara and 35kV SS Puračić-SS IV CB,
"explains the director of Energy plant, Aida Akeljić.
In addition to
decreasing the number of breakdowns and interventions on the long power lines, further
explained Aldin Kadrić, Head of the department for the production and
distribution of electricity, these activities provided their safer and more
reliable work and extended duration of the long power lines.
"The works included
the cleaning of the construction from the corrosion and putting anticorrosion
protection, the cleaning of the vegetation in and around construction pillars,
and the bursting of the vegetation on the transmission line, as well as the
cleaning and repair of damaged concrete on the corners of the foundation.
Further activities included grounding resistance measurement for each pillar, the
installation of the carrier of the pre-voltage taker, deconstruction of the
pre-voltage taker and support insulators, and installation of new ones,
cleaning of glass insulating ankles from dust and geodetic safety distance
checks, thus establishing a more stable operation of the GIKIL’s electrical
network, which further makes influence on the technical-production safety of
plant’s operation in the Company, "Kadrić adds.
In addition to these
activities, by the engagement of the company Culon doo Tuzla, significant works
were also completed at the Fertilizer plant, where reconstruction of the 6 kV facility
has been performed.
"The obsolete
low-oil switches have been removed and there was installed new equipment, of the
manufacturer "Schneider Electric", facility for the commissioning of
the 2,5 MW engine of the CR 200 compressor in the substation SS “Azotara" 35/6
kV, in order to increase the degree of reliability of the work of key engine in
the Fertilizer plant. In addition to increasing the reliability of the facility,
the reconstruction achieves more efficient and easier maintenance and also
eliminates the use of oil in the switches, which is acceptable from an
ecological point of view as well, "says Elvir Memić, Head of WU Electro
Maintenance department of the Remont plant.
The value of these
works was additionally about 38.000 KM.